Vivian Street heritage addition, Wellington |
|
|
|
|
| Project Name |
Vivian Street Heritage Apartment addition |
| |
|
|
| Project
address |
105 Vivian Street |
| |
|
Wellington CBD |
| |
|
|
| Client name |
Steven Pericos |
| |
|
|
| Project
Manager/designerSteven Young & Associates Ltd |
Steven Young & Associates Ltd |
| |
|
|
| Engineer |
Steven Young & Associates Ltd |
| |
|
|
| Consultants |
Harry Adam Engineers, Don Thompson Engineers |
| |
|
|
| Our role |
Principal consultant |
| |
|
|
| Description
of project |
Vacant office stripped back to structure, strengthened, new facade |
| |
|
added and totally refurbished |
| |
Type |
Two sdtorey reinforced concrete building |
| |
|
|
| |
Size |
450 sq metres. |
| |
|
|
| |
Value |
Approx $700,000 |
| |
|
|
| |
Date/ |
2010 |
| |
Construction period |
|
| |
|
|
| Design
features |
Existing brick wall structure and new timber addition |
| |
|
|
| |
|
|
| Special
features |
Retain existing architectural features and new added façade |
| |
|
|
| |
|
|
| Special
requirements |
Historical Trust heritage building façade |
| |
|
|
| |
|
|
| Our special
input |
Integrating facade, refurbishment and additional floor space. |
| |
|
|
| |
|
|
| What we
learned |
Uneven bricks posed difficulty in construction |
| |
|
Installation of new structural members could be tricky |
| |
|
|
| What would
we improve |
Much more detailed documentation at administration stage |
|